Re: While MIRO for Asset Purchase Order, Planned condition (For Example CVD) value is not coming automatically from PO.

$
0
0

Hi,

 

This is the standard feature ,the Quantity and amount not coming for planned Cost. In all information , if you scroll extreme right , there are fields PO Quantity and Net Value. Design the screen wherein this column are placed next to the Amount and Quantity column. The same can be copied in the field Quantity and amount for further processing.

 

Regards