Re: Availability check in planning

$
0
0

Hi AKS,

 

As per my understanding, whtever delay occur due to raw material deficit should refelect in Re Run of higher assmbly material planning.

 

You can relate your case with lead time planning. By using lead time concept changes will refelect in Re Run.

 

 

Regards,

 

Tanvir 