Check the below settings;
1) In the material master MRP views, any replenishment lead time has been set
2) In the scope of availability check (t.code OVZ9), look for the settings "Check without replenishment time" . If the field is not checked, then it uses the replenishment time of the material master to confirm.
Regards,