Re: Subcontracting WIP (Intermidiate Material)...

$
0
0

Hi Bro,

 

As you know there are two types of Subcontracting,

 

1.     Assembly Order Subcontracting

2.     Operation Subcontracting.

 

Assembly Order Subcontracting with Procurement type "X":

 

for e.g, An Order to Assembly a Ball-Point Pen. Here we give all the parts like Re-fill, Cap etc., as in In-house BOM to the vendor and after getting work done we receive as a FG "PEN" during GRN.

 

For the above case what your screen shows above is right and i tried it worked. Since the Product "PEN" has a Material Number in MM03. But My case is as below.

 

Operation Subcontracting With Procurement Type "F":

 

for e.g., My Header is a Screew with Material No. "R-F100" who's BOM has "R-B100 a 25x100mm Rod". I created a Production Order with Order type "PP01" and has the following routing...

 

0010 - Turning

0020 - Facing

0030 - Cutting

0040 - Threading

 

GI via MB1A and BOM component is assigned to 0010 - Turning and it is PCNF. I have to move this intermediate material to Vendor for operation 0020 - Facing(Via PR --> PO --> PO GRN after which it'll come to the operation 0030 & 0040 and thereby complete the in-house production order by GRN in MB31.

 

I hope i conveyed.

 

 

 

Thanks with Regards,

Dinesh V.