Hello Gurus,
we have a requirement to setup subcontracting scenario using PPM. (not linked to ECC system)
Can you please explain how the Transportation lanes & PPM should be setup.
here is what i am doing :
1. setup vendor location and create PPM in vendor location(resources from subcontracting plant are referred)
2. Tlanes (with subcontracting flag checked )are created for components from subcontracting plant-> vendor.
when i run multilevel heuristics dependent demand for the components are not getting created in vendor location & i created some requirements in RRP3 to check if the Tlane is working. but it is not.
Please help me with the master data setup.
Thanks in advance