Hi,
We would like to limit the Plant the user can enter when planning a Material Component for an Activity to the one the upper Activity, Network, WBS or Project Definition was created on (or at least Plant's within the same Company code the aforementioned objects where created on)
Right now, the Plant takes the Network's by default but the user can change it even to Plants of different Company codes.
Example:
In the Activity's Component overview:
As you can see, by default, Plant 2101 is set (Components/Items 0020 onward), this is the Activity and superior objects Plant's.
But Item/Component 0010 was allowed to be set in 3100 Plant, a plant for for another totally different Company code.
Thanks in advance for any help,